PROJECT DETAILS:
• Multinational Semiconductor Company
• Origin Site: 327,000 SF – Tampa, FL
• Destination Site: 25,000 SF – Temple Terrace, FL
• 46 Full-time Employees
• Timeframe: September 2016 – April 2017
PROJECT SCOPE:
• Schedule and Move Management
• Data Cabling and Audio-Visual Procurement
• Classified Assets and Cyber Range Relocation
• Warehouse and Machine Shop Relocation
• Environmental Test Equipment Relocation
• Shielded Enclosure Relocation and Disposal
• Disposal of 120 Truckloads (2,160 Cu. Yds.) of Debris
RELOFANT’S VALUE:
• Provided 495 Project Management and Supervisory Hours
• Managed the Relocation Effort Through a Corporate Acquisition and Restructuring
• Successfully Occupied the Destination Site and Decommissioned the Origin Site
by the Target Date