+1 813-461-7257 info@relofant.com

S&S Craftsman

,

PROJECT DETAILS:
• Molding and Casework Manufacturer
• Origin Site: 92,000 SF
• Destination Site: 30,000 SF
• Office/Manufacturing/Warehouse
• Timeframe: March 2017 – July 2017

PROJECT SCOPE:
• Budget and Schedule Management
• Tenant Improvement Construction
• Electrical Engineering and Construction
• Mechanical Engineering and Construction
• Concrete Footer Engineering and Construction
• Exterior Site Grading and Irrigation
• Overhead Door Replacement
• TPO Roof Replacement
• Dust Collection System Procurement/Installation
• Industrial Equipment Rigging
• Inventory Reconciliation and Relocation
• Furniture Procurement and Manufacturing
• Warehouse Cantilever and Pallet Racking
• VOIP Telecommunication System Integration
• Camera System Installation
• Security Monitoring and Alarm System
• Office Services Relocation Coordination
• Origin Site Decommissioning

RELOFANT’S VALUE:
• Provided Over 600 Project Management and Supervisory Hours
• Successfully Vacated the Origin Site Within the Compressed Time Frame Allotted
• Sourced and Evaluated Competitive Pricing from Multiple Vendors for Every Work Package

Skills

Posted on

March 4, 2024

Skip to content