+1 813-461-7257 info@relofant.com

Sypris Electronics

,

PROJECT DETAILS:
• Electronics Manufacturer/Defense Contractor
• Origin Site: 307,000 SF
• Destination Site: 50,000 SF
• 100 Full-time Employees
• Timeframe: May 2016 – January 2017

PROJECT HIGHLIGHTS:
• 1,560 Hours of Project Management Services
• 80 Hours of Onsite Vendor Supervision
• Sourced 2+ Bids for 13 Work Packages
• Value-Engineering for Entire TI Construction Scope
• Managed 5 manufacturing Floor Move Events Including 124 Pieces of Specialized Manufacturing Equipment Requiring 1 or More of the Following Connections: 110V / 220V / 480V Power, Data, Compressed Air, Vacuum, Exhaust, Liquid Nitrogen, Gaseous Nitrogen, and RO Plumbed Water
• Close Supervision of Trashout – 124 Truckloads (2286 CU Yds) of Debris
• A project of this magnitude typically takes 10 to 12 months. Relofant completed this project in 9 Months – with zero unscheduled downtime

PROJECT SCOPE:
• TI Construction Oversight – Change Control
• Specialty Piping
• Compressed Air, Vacuum
• Nitrogen Tank – Liquid and Gaseous
• RO Plumbing
• Document Management
• Furniture Procurement and Relocation
• Data Cabling, IT Racks
• Badge Access, Camera, Alarm
• White Noise
• Rigging
• Shelving
• Blinds
• Appliances
• Exterior Signage
• Flag Pole
• Origin Site Decommissioning

Skills

Posted on

March 4, 2024

Skip to content